2
2. Reaffirming the baseline — Any effective project review begins by assessing performance against
the established baseline. It is essential to ensure that the project review is being conducted against
the then-current project baseline. This reaffirmation should be reflected in the project report,
typically on a title page listing client and project details; project description and relevant scope of
work; contract type and approved value; and schedule, including key milestones. It is important that
the entire review team is aligned and that no assumptions about what is being discussed are
unclear. As trivial as this may seem, the author has witnessed project review meetings where
various participants had different perceptions of what was being reviewed (for example, partial
project vs. complete project).
3. Safety moment and performance — The importance of safety must be emphasized continuously
and at all levels. Selection of safety topics should reflect upcoming safety challenges the project is
likely to face. Relevance is key. At this point, safety performance from the prior period, planned
upcoming safety actions, or areas of concern should be laid out.
4. Action items — Any action items identified from the prior meeting should be brought up and their
current status reviewed. Completed actions should be formally closed out and completion
subsequently communicated as appropriate. Actions that are overdue should be examined for cause
of delay, effectiveness of management and project team efforts, and requirements and resources to
complete. Impacts of delayed completion should be assessed and any systemic issues noted for
additional follow-up and resolution. There should also be a discussion of the Decision Log,
identifying what decisions have been made since the last update, who made them and why, what
alternatives were considered, and who was informed.
5. Issues and concerns — A summary of the key issues the project team is facing should be discussed
as well as any significant concerns of the project manager. This acts to frame the rest of the project
review meeting. It allows the reviewers to agree with or challenge the project manager’s
assessment. It also helps identify other areas of concern. The status of relationships and
communication with the client and other key stakeholders should be highlighted as well as any
potential impacts on the project.
6. Value creation or value improvement — Often this discussion follows the safety moment. The
author, however, finds it to be more effective when presented in the context of the challenges and
concerns the project is facing. If a formal value improvement program is involved, including value
engineering, then that program should be discussed here and should highlight the improvements
and value (cost savings) created to date.
7. Project manager’s narrative on upcoming activities — Understanding where the project needs to
go in the short term, as presented by the project manager, should proceed the more detailed
performance review of the various project elements to date. This helps highlight the relative
importance of any deviations from planned accomplishments.
8. Changes to the baseline — It is essential to understand how the baseline has changed since the last
review meeting and from inception to date. The review team should confirm that changes were
formally approved by the client and the required contract changes received. Approved changes not
yet reflected by a formal contract change should be examined, communicated, and confirmed with
the client. Unapproved changes should not be reflected in the project baseline. Anticipated future
changes to the baseline should be discussed and those requiring timely notice confirmed. The